Hi All,
i am facing different and new issue in loadruner controller like while doing Execution with 5000 users (WEB,CRM,PeopleSoft,Oracl nca),
as soon as the testing started we notice slowness of the controller and the rate at which ramp-up is happening. The ramp-up rate was set to 90 users/minute. Previous PT with 4,600 VUsers was successful and test carried over 3 hours (including ramp-up and ramp-down). No network delays found during recent run. We checked controller logs and its captured below erros.for 4600 users and 5000 users there is no changes in scripts,LG,controller machines.
Error: Failed to start connection over firewall. No "MI Listener Name" was given,Error: Failed to start connection over firewall. No "Local Machine Key" was given, Error: Communication error: Failed to bind socket. A process on the machine is already bound to the same address. Error: Two Way Communication Error: Function two_way_comm_create_acceptor failed. Communication error: Failed to bind socket. A process on the machine is already bound to the same address., Error: Two Way Communication Error: Function two_way_comm_create_acceptor failed. , Error: Non Mdrv Message - Failed to create acceptor.
More details:
LR version-11,
total 10 LG machines,OS Windows,
LC box Ram size-20 GB
Please help me on above issue since i am in critical situation and want complete 5000 users.
Thanks,
Chinna,
9444151129.